As Launch Date looms larger and sooner the theme of checking off all the “little Big” jobs on the punch list continues although we still have a few “Big” jobs such as painting the bottom with foul release paint which continued as well this past week so without any further ado let’s jump right in to see all those jobs both little and BIG that Team Möbius looked after this week of January 25-30, 2021.

We’re Shafted!

PXL_20201027_161439955One of the “little Big” jobs that we completed this past week is getting the propeller shaft fully aligned with the output flange on the Nogva Gearbox and hence this week’s title.

In this photo the dark Burgundy is the Aft Output end of the Nogva Gearbox and the bright Red is the flange on the propeller shaft which continues through the Tides Marine shaft seal system and out of the boat through the large AL prop shaft tube which is hidden here by the Blue Tides Marine silicone bellows hose.
Nogva CPP prop   shaft dim dwg from NogvaThis dimensioned drawing of the complete Nogva CPP or controlled Pitch Propeller, shaft, seal and flange will help orient things a bit.


PXL_20201027_161424326Here I have gone below the boat rotate the CPP prop back and forth while pushing it hard forward so that the two flanges meet.  A few months back we had spent quite a bit of time getting this alignment close as we installed the anti-vibration mounts on the Gardner and the Nogva and you read about that HERE, so now it was time for the fine and final adjustment to get these two flanges perfectly aligned.
Nogva flange alignment dimsioned sketcch from installation manualAs you may recall from previous posts the two flanges need to be eXtremely closely aligned both concentrically as per the illustration on the Left and also laterally as shown on the Right.  Maximum deviation we are allowed is up to 0.005mm / 0.002in (human hair is about 0.05mm diameter) and ideally we are going for zero.
PXL_20210129_073442895.MPNeeding such perfection I called on my Perfect Partner, aka Captain Christine to assist and although she is prone to laying down on the job (sorry, couldn’t resist) she was a huge help and made this task go much faster.
PXL_20201028_093742501.MPWe check the alignment by inserting a thin feeler gauge, which is the silver strip you see here, that is a tight sliding fit into the space between the faces of these two flanges and see what the gap is at 12, 3, 6 and 9 o’clock.  Any difference in size of the gap at these locations tells us how far it is out either horizontally at 3 & 6 o’clock or vertically at 12 and 6. 
PXL_20210129_084307980Adding to the challenge the prop shaft needs to be supported in its perfectly centered position which my red hydraulic bottle jack is looking after.
PXL_20201028_093808559Mr. Gee, our Gardner 6LXB is solidly bolted up to the Nogva Gearbox so they are essentially an eXtremely solid single unit that is supported by six anti-vibration mounts such as the Silver one you can see on the Stbd. side of the Nogva Gearbox on the far Right in this photo.  You can see the large vertical threaded part of these mounts with the large supporting hex nut on the bottom and smaller locking nut on the top. 
To align the flanges vertically I need to turn the large nuts at the very front of Mr. Gee or these back two on the Nogva, Up/Down to move the Nogva flange until the gap is zero all the way around.


PXL_20201028_093728662The process then is for me to go around the four Front/Rear mounts and turn those big nuts Up/Down while Christine moved the feeler gauges around the circumference of the flanges and called out the differences in the gap to me. 

With Christine laying down in the space behind the Aft end of the ER Enclosure overtop of the Tides Marine seal at the bottom, there wasn’t enough room to take a photo but this previous shot shows what she was doing as she reached in with the feeler gauges to check the gap and call out the differences to me.  Doing this all by myself was very time consuming so now you see what I called in the Big Boss to help out! 

It still took us almost 2 hours but in the end we got the gap down to zero such that both flanges were touching all the way around. 
PXL_20210129_084325319With these two flanges now fully aligned we could insert the 8 hardened Grade 8 bolts through both flanges and torque them down to 120NM and the alignment was done! 

White grease is TefGel 45 to prevent any corrosion and ensure that these nuts are just as easy to undo after many years on the job when we need to remove the prop shaft or the Nogva/Gardner for some reason in the distant future.
Tides Marine SureSeal illustrationMany of these “little Big” jobs are like dominos in that as getting one done lets you do the next.  So with the flanges aligned and mounts all torqued down I could now finish installing the Tides Marine SureSeal system. This is an eXtremely critical bit of kit as this is responsible for keeping the prop shaft cutlass bearing lubricated with a flow of fresh sea water AND keeping that sea water OUT of the boat!
PXL_20210129_124430339Here is what the real deal looks like now fully installed.  The Blue silicone “Articulating hose” in the illustration above, is double clamped onto the Stern or Prop Shaft Tube at the bottom and onto the Black SureSeal housing at the top. 

The way this works is that inside the SureSeal are two stationary rubber lip seals with the 65mm OD Prop Shaft rotating inside them that keeps the water sea water inside the Prop Shaft Tube from being able to get past and into the boat. 

We keep a VERY close eye on that Blue silicone hose over the years as if it were to ever rupture we would have an eXtremely large volume of water flooding into the boat!

FYI,
The Black ring at the top is the very handy holder for a second set of replacement lip seals which you can change out with the boat still in the water as you don’t have to remove the Prop Shaft to replace them; just pry the old ones forward, cut them off and slide the new ones into place.


PXL_20210129_124446081Last part of installing the SureSeal system is to provide a pressurized flow of fresh sea water into the Prop Shaft Tube which travels down the tube and lubricates the Cutlass bearing which supports the Prop Shaft as it exits the boat.

One of the reasons I chose to locate the Silver Heat Exchanger you see in the Upper Right was to be able to tap into its drain plug on the salt water side and use this as the source of pressurized salt water for the SureSeal.  Nice short hose run and Cihan had that all hooked up in no time.  The second Red hose on the Left goes up along the Aft wall of the ER with a ball valve on the end of it so that I can check the salt water flow rate when we first start up and from time to time afterwards and ensure that there is at least 4L/min / 1USG/min when the engine is idling.
PXL_20210129_124414968.MPBoth those little Big jobs checked off the list and this is what the finished result looks like when peering down into the space Christine has now vacated on the outside of the Aft wall of the ER.  Silver Gardner Coolant Heat Exchanger bottom right, Tides Marine SureSeal middle Left and Red Prop Flange middle Right and the Red Nogva Gearbox Oil Heat Exchanger at the top.

To keep the ER air tight a 6mm AL plate is bolted with a gasket over top and covered wtih the same composite grid floor plates as the rest of the Workshop and ER.
Heat Exchangers labelledCihan checked off another Big little job by plumbing the Sea Water and Engine Coolant water lines up at the forward Starboard/Right corner of Mr. Gee and the ER.  It is pretty busy up there so I’ve labelled some of this plumbing to help you make sense of it.  Can be a bit confusing as there are three fluids running around here; Sea Water that comes in via the Sea Chest just visible on the far middle Right here and through the Strainer and Manifold on its way to the Jabsco Impeller Pump and then out of that Pump and into the Engine Oil Heat Exchanger where it runs Aft exiting out and into that Silver Sea Water Heat Exchanger you saw up above in the SureSeal installation sequence.

Hope you got all that because YES children that WILL be on the Test on Friday!

Driving Big Red #2

Electrodyne #2 jack shaft labelledOver on the opposite Port/Left side of Mr. Gee I finally have the drive system for our second Electrodyne 250Ah @ 24V alternator all designed and the adapters all machined so time to get them all installed.  You may recall this photo from THIS previous blog post about installing what I call Big Red #2 and how I intended to drive it from the PTO or Power Take Off on the Gardner using a Jack Shaft I had from a previous job.
Jackshaft renderThis is a quick screen shot from my Fusion 360 design for the adapters at either end of the Red JackShaft.  Green cylinder on the far Left is the Output shaft from the Gardner PTO, Purple is the AL adaptor to couple the Jackshaft to the PTO and at the far Right in Gold is the steel multi V-belt drive pulley that came with the Electrodyne which I will machine with four threaded holes to bolt the other end of the Red Jackshaft to. 


Note: Jackshaft simplified here to just a rod with flanges at either end.


PXL_20210130_125654649This is the PTO from the Gardner with that Purple aluminium adaptor in the rendering above now pushed onto the Green PTO Output shaft and secured with four round hex head through bolts. 

The Red Flange on the front U-joint end of the JackShaft barely visible on the Right will bolt to that AL adaptor with four more M6 SS bolts.
PXL_20210130_125702007This is the Aft end of the JackShaft where this U-joint will be similarly bolted to that steel 8V pulley on Big Red #2.
PXL_20210130_125713105The day came to an end at this point yesterday so not quite finished but this shot will show you how the whole JackShaft will connect the power from the PTO back to Big Red #2.  This monster Electrodyne alternator could absorb as much as 10HP at full 250 amps of output which the gear driven PTO can put out easily and this Cardan or Jack Shaft should be more than up to the task.

Stay tuned for more though folks on the final installation of Big Red #2 next week AND just wait till you see the sweet setup I’ve come up with to drive Big Red #1 using a cogged timing belt setup that is now almost done.

Well Sand My Bottom!

PXL_20210125_083618470Also not quite done but work continued this past week on getting the bottom underwater portion of the hull all primed and filled in preparation for applying the silicone based Foul Release paint, International InterSleek 1100SR.

The Paint Crew finished applying all the epoxy filler to smooth out all the welds and create a sleek smooth surface for the InterSleek 1000SR Foul Release top coat to come.

You can see some of the filled welds around the Prop Tunnel above and
PXL_20210125_113912527….. the filleted edges around the AL threaded mounting disk for the Zinc on the Rudder.  The circle on the Right is the filled in through hole we put in the Rudder to make it possible to remove the Prop Shaft without having to drop the Rudder.  Because we hope to not need to remove the Prop Shaft for many years this hole is filled in to provide a fully flush curved surface on the Rudder sides to maximize a smooth laminar flow of water over the Rudder.
PXL_20210125_113934869.MPSanding the first coat of epoxy filler on the Keel and Prop Tunnel into smooth large radius coves.
PXL_20210126_114206167….. and the Aft Depth Sounder transducer.
PXL_20210126_114219496….  and one of the 5 Sea Chests.
PXL_20210126_114321477By end of the week they had the last of the 5 coats of International epoxy primer rolled as you can see around the Bow Thruster Tunnel, another smaller Sea Chest intake and Zinc mounting disk up near the bow.
PXL_20210126_114402759Final coat of epoxy primer being rolled on Aft and we’ll see the application of the InterSleek 1100SR next week.

Grand Dame of Dyneema!

PXL_20210129_144503223.MPLest you should think that The Captain only lays down on the job, this will prove that she sometimes sits! 
PXL_20210129_144634649But Christine has become and expert Dyneema splicer after doing so many as she installs  all the Lifelines around the Main Deck.  This are the AL Stanchions with their Lifelines now in place on the Aft end of the Port/Left side.  The Tender will come On/Off this side so these 3 LifeLines have Pelican Hooks that are easy to release so we can then pull up the Stanchions and roll up the whole setup and stow when the Tender is aboard.
PXL_20210129_144622216Closer view of how these Pelican Hooks and Thimbles work.
PXL_20210129_144628144You start to appreciate how Christine’s Dyneema splicing expertise has developed so quickly when you start to count up all the splices required for each LifeLine in the system we’ve come up with.  On the far Right is an endless loop that wraps around the AL Stanchion through a small AL D-ring to keep it in place and a SS Thimble captured on the end.  Last step of this will be to lash the loop around the SS Thimble closed so that when it is undone the Thimble can’t come out.


Tylaska Dyneema AL rings donutsLooking down the LifeLines to the Left you can see another splice at the Left end of the Pelican Hook and then further Aft/Left two more around these Black anodized Donuts or Rings you can see further to the Left.  Christine leaves a gap of about 80-100mm / 3-4” between these two rings and then wraps multiple lashings between them to tension the life lines.  And of course each of these Rings require yet another splice!

INTERIOR UPDATES:

PXL_20210125_091302262.MPHilmi and Ramazan continued their work inside Möbius this past week and we also find more of Captain Christine’s fingerprints up here at the Main Helm where she and Hilmi have been working to install and connect Boat Computer #1 you see here on the Port/Left side of the Main Helm Chair.
PXL_20210125_091330861Its ultimate home will be inside this space behind the 50” Monitor on the outside and this AC/Heating Air Handler inside.
PXL_20210125_091339930This space is normally covered by this hinged Rosewood back with a recess for the adjustable mounting system for the 50” monitor that doubles as both our movie watching entertainment screen when on anchor and then one of 4 screens for boat data and navigation when underway.
PXL_20210126_075505032Down in the Guest Cabin Ramazan is completing the last of the Ado LVT vinyl plank flooring. 
PXL_20210126_075450320.MPWhile the smallest by surface area it has ELEVEN removeable sections above the bolt on tank access hatches below so this area is taking the most time.

Pull out Bed in the Upper Left and Christine’s Office desk on the Right.
PXL_20210127_110131943.MPSix of those removable floor sections all weighted down while the adhesive dries.
PXL_20210126_153010788.MPRemovable floor sections?

What removable floor sections?
PXL_20210129_095901473Ramzan then stepped up his game (sorry) by moving up to install the vinyl flooring on the steps leading up from the SuperSalon to the Aft Deck. 

Another tricky and time consuming bit of detail as each step has one of these handrail posts he needs to go around.
PXL_20210129_095827835Which, as you can see, he had no trouble doing eXtremely well!
And that’s a wrap for the week that was January 25-30, 2021.  Yikes!  The first month of 2021 gone already??? 

Well at least it puts us another week closer to LAUNCH so as with “being shafted” that is all a very good thing.

Thanks for joining us for yet another episode here at Möbius.World.  REALLY appreciate and value you doing so and please feel encouraged to add your comments and questions in the “Join the Discussion” box below.

Hope to see you here again next week.

-Wayne